SL- Road Sector Assistance Project 
 
The Sri Lanka Road Sector Assistance Project aims to lower transportation costs through sustainable delivery of an efficient national road system that serves the needs of road users and the Sri Lankan public at large. There are three project components: 1) Maintenance and Rehabilitation of National Roads Component: This consists of (a) civil works along national roads comprising resurfacing and improvement of about 620 km of Class A and B roads; (b) technical assistance for the selection, and the design and construction supervision of these works; (c) training and institutional strengthening; and (d) goods and incremental operating costs. 2) Maintenance and Rehabilitation of Rural Roads Pilot Component: This consists of (a) developing a strategy for the management of rural roads; (b) rehabilitation and maintenance of about 635 km of rural roads in nine local government areas (Pradeshiya Sabhas) whose selection is based on the recently completed poverty map for Sri Lanka; (c) training and institutional strengthening; and (d) goods and incremental operating costs. 3) Institutional Strengthening and Policv Support Component: This component comprises technical assistance to implement improved sectoral policies for road maintenance financing.** 
  Last Updated  September 03 2010
Basic Information
Project StatusActive 
Region South Asia 
Country/AreaSri Lanka 
Major Sector (Sector) (%) Transportation (Roads and highways) (90%) 
  Public Administration, Law, and Justice (Central government administration) (6%) 
  Public Administration, Law, and Justice (Sub-national government administration) (4%) 
Old Major SectorN/A  
Old SectorN/A  
Env CategoryB  
Project IDP086411 
Bank Team Lead (Last Name, First)Rajapaksa, Amali  
Approval Date15-DEC-2005  
Closing Date30-SEP-2011  
BorrowerTHE GOVERNMENT OF SRI LANKA  
Implementing AgencyROAD DEVELOPMENT AUTHORITY (RDA) & MIN HOME AFFAIRS, PC, LG  

Financial
Main Loan/Credit #44290  
IBRD Commitment *
IDA Commitment *100 
IBRD + IDA Commitment *100 
Grant Amount *
Total Project Cost *144.12 
Product LineIBRD/IDA 
Lending InstrumentSpecific Investment Loan 

Development Outcomes And Goals
Targeted Thematic Outcomes...Supporting this Broader Dev't Goal
Environmental policies and institutionsEnsure environmental sustainability (MDG); Environmental commons (GPG)
Social analysis and monitoringEmpowerment, security & social inclusion (CAP); N/A (GPG)
Infrastructure services for private sector developmentN/A (CAP)
Rural services and infrastructureN/A (CAP)
Administrative and civil service reformPublic sector governance (CAP)
Available Project Documents***
For a short project overview, please consult the Project Information Document if available.
 
Procurement Plan (PROP), Vol.1 -30-SEP-2009 
Procurement Plan (PROP), Vol.1 -20-FEB-2009 
Financing Agreement (), Vol. -16-SEP-2008 
Project Paper (PJPR), Vol.1 -23-JUN-2008 
Procurement Plan (PROP), Vol.1 -07-DEC-2007 
Environmental Assessment (EA), Vol.5 -01-FEB-2006 
Environmental Assessment (EA), Vol.4 -01-FEB-2006 
Environmental Assessment (EA), Vol.3 -01-FEB-2006 
Credit Agreement (), Vol. -16-JAN-2006 
Project Appraisal Document (PAD), Vol.1 -16-NOV-2005 
Integrated Safeguards Data Sheet (ISDS), Vol.1 -30-SEP-2005 
Integrated Safeguards Data Sheet (ISDS), Vol.1 -20-SEP-2005 
Environmental Assessment (EA), Vol.1 -07-SEP-2005 
Project Information Document (PID), Vol.1 -30-AUG-2005 
Environmental Assessment (EA), Vol.2 -01-MAY-2005 
Integrated Safeguards Data Sheet (ISDS), Vol.1 -22-DEC-2003 
Project Information Document (PID), Vol.1 -22-DEC-2003 
 
Contract Award Information
 
Click here to see contract award information about this project.

*Commitment at Board in USD$ millions. Does not reflect any cancellations. Pipeline and dropped projects display the forecast amount. Total project cost includes non-Bank funding.

** The project summary is drawn from the PAD, SAR, or PGD abstract and may not accurately reflect the project's current nature.

*** Project documents are posted to this website as soon as they reach certain milestones (more info.). For example, Project Appraisal Documents are processed and made available through this website a few days after Board approval. If you find that a report which should be here is unavailable, contact Infoshop .